Skip to main content

Active Projects

Commenced January 2025

Carter Hill Tank Project

Estimated Project Cost: $12,000,000
LEARN MORE

The Carter Hill tank site, located adjacent to the Nunes Water Treatment Plant, currently has three water storage tanks at the site: HMB 1: built 1950, .4 million gallons; HMB 2: built 1955, .6 million gallons; and HMB 3: built 1963, 1.5 million gallons.

The Carter Hill Prestressed Concrete Tank and Seismic Upgrades Project involves the demolition and removal of tanks HMB 1 and HMB 2 and existing yard piping, and constructing a new 2.1 million gallon AWWA D110 Type 1 Prestressed Concrete DN Tank and new yard piping and related infrastructure. The project commenced January 2025 with scheduled completion in Spring of 2026.

Staff Report – July 9th, 2024 – Board Meeting (PDF)
Staff Report – March 11th, 2025 – Board Meeting (PDF)
Project Signage (PDF)


Completed Projects

Completed July of 2025

Highway 92 Pipeline Replacement Project Phase 1

Estimated Project Cost: $3,000,000
LEARN MORE

During December 2022/January 2023 winter storms, erosion from the storms exposed segments of the buried pipeline. A temporary bypass 2-inch pipeline adjacent to Highway 92 was installed above ground leaving it at risk to damage and not suitable for long-term use. During a previous storm, another segment of Pipeline was exposed near the Corinda Los Trancos Creek, also putting it at risk for failure. Therefore, this project includes installation of a 12-inch diameter high density polyethylene (“HDPE”) pipe via horizontal directional drilling under Corinda Los Trancos Creek and two crossings of Pilarcitos Creek, with the rest of the pipeline consisting of 10-inch and 6-inch diameter ductile iron pipe installed via open trench. The total length of the new water main is 5,665 linear feet.

7 Day Construction Notice in English and Spanish (PDF)

  • Highway 92 Pipeline Replacement Project Phase 1 map with legend
    • Advantage Reline video showing Magellan/Hwy 1 Pipeline Restoration Project using Primus Line to line existing cast iron pipeline.

      Completed July of 2024

      Magellan/Highway 1 and Alameda Avenue Pipeline Restoration Projects

      Project Cost: $500,000
      LEARN MORE
      Magellan/Highway 1 Portion of the Project

      Approximately 475 linear feet of existing 10-inch cast iron pipe was lined with Primus Line, a flexible fabric pipeline liner. This process was performed using the Primus slip lining technique, which avoided causing any disruptions on Highway 1 and the Coastal Trail, and saving the District $2M+ in pipeline replacement costs using traditional methods.

      Alameda Avenue Portion of the Project

      Around 175 linear feet of the existing 10-inch welded steel pipeline were lined with Primus Line, a flexible fabric pipeline liner.

      Completed June of 2024

      Nunes Water Treatment Plant Improvement Project

      Project Cost: $10,450,000
      LEARN MORE

      The District has completed upgrades to its Nunes Water Treatment Plant in Half Moon Bay, California. There were numerous improvements made during the 3 years, which included the following main items of work: a new plate settler sedimentation basin, a new caustic soda storage tank, site improvements, filter improvements, clearwell improvements, and electrical/instrumentation improvements. These upgrades provide operational redundancy and efficiency at the treatment plant, so that it has backups in case of equipment failure, allowing for quick restoration of normal operations without significant disruptions to water service.

      Staff Report – July 5th, 2024 – Board Meeting (PDF)

      “We invested a lot of money, but we got an enormous bang for the buck.”

      Director Glenn Reynolds

      Completed June of 2024

      Valve Replacement Project

      Project Cost: $300,000
      LEARN MORE

      This project involved replacing 15 water main valves in disrepair, removal of a 6″ water main that crossed behind several backyards along 2nd Avenue (between Granelli Avenue and Myrtle Street), and installation and connection of approximately 50 linear feet of new 6″ ductile iron pipe water mains.

      Completed February of 2024

      Poplar Street Water Main Replacement Project

      Project Cost: $416,000
      LEARN MORE

      Prior to the commencement of the City of Half Moon Bay’s Poplar Street Traffic Calming and Safety Project, CCWD replaced 850 feet of existing cast iron main with new ductile iron pipe, domestic services and operating valves adjusted to the new street profile.

      In Process/Future Projects

      • Scheduled to start December 2025:

        Pilarcitos Canyon Well Replacements

        PROJECT ESTIMATED COST: $1,000,000
      • Scheduled to start Spring 2026:

        Scheduled Pipeline Replacements

        PROJECT ESTIMATED COST: $1,000,000+
      • Scheduled to start Summer 2026:

        Pilarcitos Canyon Road Repairs

        PROJECT ESTIMATED COST: $400,000

      Major Projects Completed in the Last 5 Years

      • July 2025

        Highway 92 Pipeline Replacement Project Phase 1

        PROJECT COST: $3,000,000
      • July 2024

        Magellan/Highway 1 and Alameda Avenue Pipeline Restoration Projects

        PROJECT COST: $500,000
      • June 2024

        Nunes Water Treatment Plant Improvement Project

        PROJECT COST: $10,450,000
      • June 2024

        Valve Replacement Project

        PROJECT COST: $300,000
      • February 2024

        Poplar Street Water Main Replacement Project

        PROJECT COST: $416,000
      • June 2023

        Grandview Water Main Replacement Project

        PROJECT COST: $1,900,000
      • February 2023
        Pipe Under Creek-Pilarcitos-Strawflower
        PROJECT COST: $700,000
      • January 2023
        Crystal Springs Pump Replacement Project
        PROJECT COST: $300,000
      • June 2022
        Nunes Fuel Tank Upgrade Project
        PROJECT COST: $200,000
      • June 2021
        Denniston Water Treatment Plant and Booster Pumpstation Emergency Power/Generator Project
        PROJECT COST: $600,000
      • August 2020
        Denniston Water Treatment Plant/Denniston Tank Road Repairs
        PROJECT COST: $500,000
      • June 2020
        Ferdinand Avenue Pipeline Replacement Project
        PROJECT COST: $650,000
      • May 2020
        Pilarcitos Canyon Pipeline Replacement Project
        PROJECT COST: $1,400,000
      • February 2020
        Casa Del Mar & Grand Avenue PRV and Pipeline Replacement Project
        PROJECT COST: $650,000